​Project at a glance

Client: KVK Koerner

Location: Denver, NC

Scope: Installation of (2) 80,000 lb process tanks

Equipment: 400 Ton Gantry System, 75 Ton Mobile Lift, 275 Ton - All Terrain Crane, 15,000 LB Forklifts, 25 Ton Carry Deck Crane

Completion: September 2024

 

Project Overview

AMS partnered with KVK Koerner to install two 80,000 lb process tanks at a galvanizing facility in Denver, North Carolina. The project required precise coordination, controlled lifting, and experienced execution to safely place critical equipment within the plant.

 

The Challenge

Installing large-scale process tanks inside an active industrial environment comes with zero room for error. The weight, size, and sensitivity of the equipment required detailed planning, proper rigging configurations, and careful maneuvering to ensure safe placement without disrupting surrounding operations.

 

Our Approach

AMS developed a lift plan tailored to the site conditions and equipment specifications. Our team coordinated crane selection, rigging setup, and on-site logistics to ensure a smooth and controlled installation process.

With experienced operators, certified rigging crews, and proper lift execution, we were able to safely handle and position both tanks with precision.

 

The Result

Both 80,000 lb tanks were successfully installed on schedule and without incident. The project was completed safely, efficiently, and to the exact specifications required by KVK Koerner and the facility.

 

Planning a tank installation?

Explore our crane services or request a project quote. Share the tank dimensions, weight, placement drawings, site access and target dates so AMS can review your scope.